Crescent Dunes Solar Thermal Power Plant

Scope of the project

IPROCEL participated in the commissioning of the Crescent Dunes Solar solar thermal plant, with an installed capacity of 110 MW, located in the United States and promoted by the Cobra Group.
The scope of work included:
- Coordination and supervision of the commissioning activities of energy generation, storage and evacuation systems.
- Verification of the correct integration of the control and protection systems with the SCADA system.
- Performance and monitoring of functional and operational tests to ensure compliance with technical and safety standards.
- Support in the training of operating personnel and in the preparation of the technical documentation necessary for the operation and maintenance of the plant.
With this project, IPROCEL continued its growth in the US market, adapting to the different opportunities that arose in both the renewable energy and conventional sectors, thus consolidating its presence and experience in the country.

Power

110 MW

Location

United States

Customer

Cobra Group